Elevator "Going Up"

The elevator shaft construction is commenced.   Since its foundation is 5'  below the basement, the building must be underpinned, then the new shaft commenced.  Compressors, power and drains located in this area are relocated.    (Click Images for more info)

Previous
Previous

Phase One Finish Work

Next
Next

Green Roof Installation